AI-Driven Financial Risk Forecasting for Robotic Construction Projects Through Predictive Analytics and Adaptive Resource Allocation
Keywords:
construction robotics; financial risk forecasting; predictive analytics; conditional value-at-risk; resource-constrained scheduling; quantile regressionAbstract
Robotic construction projects concentrate financial exposure in a small number of resource-constrained, technology-intensive activities: robot deployment, task execution, material handoff, and schedule recovery. Conventional earned-value and deterministic critical-path forecasts do not represent robot-specific downtime, nonlinear resource productivity, or the joint effect of schedule and cost uncertainty. This manuscript develops an integrated predictive-analytics and decision framework for financial risk forecasting in robotic construction. The framework converts building information modeling quantities, enterprise resource planning commitments, robot telemetry, supply conditions, and schedule state into a task-level risk state; estimates quantile forecasts of cost overrun, delay, and idle-resource loss with ensemble learning; and calibrates these forecasts for use in risk-sensitive resource allocation. Allocation is formulated as a stochastic program that minimizes expected financial loss plus a conditional value-at-risk penalty subject to robot, crew, material, and budget constraints. A finite-quantile representation links predictive distributions to optimization and yields a contingent-reserve rule that separates expected cost from tail exposure. The paper analyzes error modes, calibration requirements, distribution shift, and the trade-off between robust and opportunistic allocation. Its main contribution is a coherent forecasting-to-decision architecture that treats financial risk as a dynamic, resource-dependent quantity rather than a post hoc project-level variance. The framework provides a technically defensible basis for budgeting, contingency planning, and adaptive scheduling in robotic construction while identifying conditions under which predictive control improves decisions.
References
1. Bock, T. (2007). Construction robotics. Autonomous Robots, 22(3), 201–209.
2. Bock, T., & Linner, T. (2016). Construction robots: Elementary technologies and single-task construction robots. Cambridge University Press.
3. Saidi, K. S., O'Brien, J. B., & Lytle, A. M. (2008). Robotics in construction. In B. Siciliano & O. Khatib (Eds.), Springer handbook of robotics (pp. 1079–1099). Springer.
4. Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003). Megaprojects and risk: An anatomy of ambition. Cambridge University Press.
5. Flyvbjerg, B., Holm, M. S., & Buhl, S. L. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American Planning Association, 68(3), 279–295.
6. Gondia, A., Siam, A., El-Dakhakhni, W., & Nassar, A. H. (2020). Machine learning algorithms for construction projects delay risk prediction. Journal of Construction Engineering and Management, 146(1), 04019085.
7. Wauters, M., & Vanhoucke, M. (2016). A comparative study of artificial intelligence methods for project duration forecasting. Expert Systems with Applications, 46, 249–261.
8. Breiman, L. (2001). Random forests. Machine Learning, 45(1), 5–32.
9. Koenker, R., & Bassett, G. (1978). Regression quantiles. Econometrica, 46(1), 33–50.
10. Luo, D., & Yu, L. (2021). From factory to site—designing for industrial robots used in on-site construction. In Automating cities: design, construction, operation and future impact (pp. 87-109). Singapore: Springer Singapore.
11. Rockafellar, R. T., & Uryasev, S. (2000). Optimization of conditional value-at-risk. Journal of Risk, 2(3), 21–42.
12. Artzner, P., Delbaen, F., Eber, J. M., & Heath, D. (1999). Coherent measures of risk. Mathematical Finance, 9(3), 203–228.
13. Romano, Y., Patterson, E., & Candès, E. J. (2019). Conformalized quantile regression. In Advances in neural information processing systems (Vol. 32, pp. 3543–3553). Curran Associates.
14. Hartmann, S., & Briskorn, D. (2010). A survey of variants and extensions of the resource-constrained project scheduling problem. European Journal of Operational Research, 207(1), 1–14.
15. Kolisch, R. (1996). Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation. European Journal of Operational Research, 90(2), 320–333.
16. Birge, J. R., & Louveaux, F. (2011). Introduction to stochastic programming (2nd ed.). Springer.
17. Bertsimas, D., & Sim, M. (2004). The price of robustness. Operations Research, 52(1), 35–53.
18. Sacks, R., Eastman, C., Lee, G., & Teicholz, P. (2018). BIM handbook: A guide to building information modeling for owners, designers, engineers, contractors, and facility managers (3rd ed.). Wiley.
19. Tao, F., Zhang, H., Liu, A., & Nee, A. Y. C. (2019). Digital twin in industry: State-of-the-art. IEEE Transactions on Industrial Informatics, 15(4), 2405–2415.
20. Vanhoucke, M. (2012). Project management with dynamic scheduling: Baseline scheduling, risk analysis and project control. Springer.
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Journal of Advanced Financial Research

This work is licensed under a Creative Commons Attribution 4.0 International License.